Assign employees to activities
Requirements: In order to assign employees to activities,
you need to first assign personnel resources in the form of roles.
In order to semi-automatically assign employees to activities,
you do the following:
- Select the menu item Project / Assign
employees to activities.
The dialogue box Assigning employees - Step 1 of
3: Selection of employees opens.
The list includes all the employees you can assign to activities
or reassign to other activities by selecting them in Step 1.
Employees are grouped together in teams, while employees not
being part of a team are shown at the lower end of the list.
- Calendar - predefined calendar of the
employee.
- Week - average working hours per
week.
- On-call - percentage of the possible
working capacity of an employee within project duration, adjusted
for the reported non-working days (holidays/sickness).
- Click the check boxes of the employees you would like to assign
to activities in the column No..
You may also click on the button Select all
employees.
- Click on the button Continue.
The dialogue box Assigning employees - Step 2 of
3: Selection of activities opens.
This list provides you with all the activities you can later
assign employees to.
- The activities provided for selection reflect the structure of
the project.
- Click on the check boxes for the activities to whom you want to
assign employees.
You may also click on the button Select all
employees.
- Click on the button Continue.
The dialogue box Assigning employees - Step 3 of
3: Assigning employees to activities opens.
This list includes all the selected employees you can assign to
the selected activities in Step 3.
Employees can be assigned to an activity if their role and
qualification meets the demands of the activity.
Assignations are automatically evaluated and have an effect on
succeding activities (white: assignation possible, grey:
assignation not possible as already covered by an employee, red:
assignation possible, but timing conflicts occur).
- On-call - percentage of the possible
working capacity of an employee within activity duration, adjusted
for the reported non-working days (holidays/sickness).
- Role - role of the employee.
- Effort - number of required employees for
the activity and effort.
- Start - scheduled start of the
activity.
- Finish - scheduled finish of the
activity.
- Click on the check box for the activity you want to assign to
an employee (for instance, because the employee can be on-call for
100% of the total activity duration).
Assignation options are dynamically adjusted.
Note: When assigning, we recommend you using the
following strategy to avoid overload of resources: first assign
activities to employees who can cover activities at 100% (column
On-call) and productivity at 100%.
- Repeat Step 6 if necessary.
You may also click on the button Assign employees
automatically.
- Click on the button Finish.
Important! Possible conflicts and overloads are indicated
in red, and there is no automatic assignation.
See also:
Setting and adjusting
roles,
Setting and adjusting
teams,
Setting and adjusting
employees,
Setting and adjusting
materials,
Setting and adjusting
machine types,
Setting and adjusting
machinery.
|