Edit link
Links can only be edited as long as the succeding activity has
not yet started.
In order to change an existing link, do as follows:
- Mark the link you want to edit by clicking on the line
connecting the two activities.
- From the drop down menu Link type, select
another link type in the properties window.
- If wished, enter the Delay (positive or
negative) by which you want to delay the succeeding acticity
depending on the selected type of activity.
- Click on the button OK.
Alternatively: You can change the Link
type via the context menu of the connecting line.
|