Link activities
Activities can be linked with each other in bar diagrams network
diagrams and bar-network diagrams.
The following link types are at your disposal:
|
Finish-Start
|
the "from" activity must finish before the "to" activity can
start |
|
Finish-Start without delay
|
the "from" activity starts after the finishing of the "to"
activity with a minimal delay |
|
Start-Start
|
the "from" activity must start before the "to" activity can
start |
|
Finish-Finish
|
the "from" activity must finish before the "to" activity can
finish |
|
Start-Finish
|
the "from" activity must start before the "to" activity can
finish |
|
Incompatible activity group
|
Activities that must not be executed at the same time (timing
conflicts) |
You can unhide the Properties window of any link by
doubleclicking on the link.
Intervals
Intervals can be defined in Project properties in relation to
the time unit of the duration (such as hours or days).
You can choose among the following types of intervals:
- in absolute time (estimated duration including non-working
days, such as: 10 hours or 2 days)
- in calendar time (depending on the current calendar, that is,
it ignores non-working hours, such as: 3 working days)
- in relative time (for instance, a particular percentage,
relating to the "to" activity, such as: 50%)
Intervals can have
- positive (such as: + 2 hours) or
- negative (such as: - 50% = overlapping)
signs.
Highlight link
Links can be highlighted by means of colour or boldface.
Create link
In order to create a new link, do as follows:
- Choose the link type via the appropriate icon buttons in the
tool bar.
- Describe a connection by drawing your mouse from one activity
to another.
- Choose the interval type for the link in the Properties
window.
- If wished, enter the Delay (positive or negative) by which you
want to delay the "to" acticity depending on the selected type of
link. If you have entered a delay, click on the button
OK.
Alternatively: You can link activities in the diagrams
via the context menu.
Notes (restrictions in the creation of links):
- Only one link Finish-Start without delay
can succeed an activity (the amount of succeeding links Finish-Start can be unlimited).
- Only one link Finish-Start without delay
can precede an activity (the amount of preceding links Finish-Start can be unlimited).
- The occurrence of an activity is only allowed in incompatible
activity groups.
|