Human Resource Capacity Leveling
If the scheduling of roles and machine types is completed, the
view Capacity alignment personnel helps you estimate whether there
is sufficient personnel capacities to execute the project or where
potential bottlenecks may occur.
The Capacity alignment personnel is determined by the
number of employees, their qualifications, time of employment and
place of work (project, subproject). The Capacity alignment
personnel not only shows the number of the required hours and
days for employees and roles, but also indicates ecxess and
shortfall (supply minus demand = contingency). Moreover, the view
Capacity alignment personnel helps you detect employees that
match the requirements of the demand.
Employees whose employee hours / days are in boldface, have
already been assigned to this activity. If they are displayed in
both boldface and red colour, you have an assignation conflict,
which means that the employee has been assigned to several
activities at one time.
You can use the Human Resource Capacity Leveling to do
the following:
- Detect overloaded resources as well as the scale and cause of
this event.
- View the working capacity for each of the resource role.
- Calculate the numbers of work hours that have been assigned to
the individual employees.
- Determine the time the employee is available for additional
assignments.
Context menu in the view Human Resource Capacity Leveling
- Expand/collapse all resources – Depending on the
preferred view, you can expand/collapse all resources.
- Show maximum per time unit – The maximum required number
of personnel resources for each of the roles / qualifications per
day, week, etc.
- Show effort per time unit – Planned effort in employee
hours (or employee days, respectively) per day, week, etc.
- Group by roles – Presents the qualifications belonging
to a role in one row with total utilization.
- Place activities in one row, if possible - Displays the
activities done by one role in one row, if possible.
For better presentation, activities overlapping in time are shown
in separate rows.
- Display in reference to subprojects - The resource
utilization is not shown for the overall project, but for each of
the subprojects separately. However, only those subprojects are
considered that are on the level immediately below the overall
project.
- Unhide activities – Depending on the preferred view, you
can hide or unhide activities.
- Unhide employees – Depending on the preferred view, you
can hide or unhide employees.
- Sort roles – All displayed roles can be sorted along
number, name or code.
- Sort activities – All displayed activities can be sorted
along number, start date and finish date.
- Sort employees – All displayed employees can be sorted
along number, name, code or cost per hour.
- Additional resource diagram – You can view an additional
resource diagram in the lower area of the window Role
utilization.
- Additional break-even chart – You can view an additional
break-even chart in the lower area of the window Role
utilization.
|