Control of project financing
In order to evaluate the financing of the project, you do as
follows:
- Open an additional break-even chart for the bar diagram in the
menu item View / Additional break-even chart.
- Record all expected incoming payments by setting a separate
milestone at the date of invoice.
- The break-even chart contrasts the actual costs with the
financing. The the dates of invoices are marked at the curve Actual
costs.
Note: The financing can be displayed either by the dates of
invoices or the payment deadline.
- You can use the menu items View / Show
financing - date of invoice and Financing -
payment deadline to toggle between View / Show
financing - date of invoice and Financing -
payment deadline.
- Similar to the date of invoice, the dates that are identical
with the payment deadline are highlighted at the curve Actual
cost.
The financing control allows you therefore to detect risks in
investments (advance financing).
|