Optimise a project
The purpose of the optimisation of a project is to obtain a
project schedule that meets a predefined deadline and which makes
optimal use of resources.
In order to optimise a project, go to the menu item Project / Optimise resource utilization.
Note:
- You can use the check box Fix in the
window Activity properties (tab General, field
Due date) to ensure that the due date of the
activity remains unchanged during optimisation.
- The optimisation process takes the fixed dates of the
subprojects into account.
- The command Optimise resource utilization
in the context menu of the subproject can be used to optimise
selected subprojects only.
- The optimisation of personnel resources is done along the
following command structure: employees -> teams -> roles
(explanation: if it includes employees, the optimisation will
ignore teams or roles.)
Contingency reserve
The display of the contingency reserve provides an overview
about the erliest possible start dates and latest possible finish
dates of activities and subprojects in the bar diagram in the event
of changes to the project schedule.
In order to activate the view of the contingency reserve, do as
follows:
- Select the menu item Tools / Global
settings.
- In the tab, select General.
- Mark the check box Calculate contingency
reserve.
- Select the menu item View / View contingency
reserve.
|