Optimise a project
The purpose of the optimisation of a project is to obtain a
project schedule that meets a predefined deadline and which makes
well-balanced use of resources.
In order to optimise a project, go to the menu item Project / Optimise resource utilization.
A project without resource optimisation.
A project after resource optimisation.

Note:
- You can use the check box Fix in the
window Activity properties (tab General, field
Due date) to ensure that the due date of the
activity remains unchanged during optimisation.
- The optimisation process takes the fixed dates of the
subprojects into account.
- The command Optimise resource utilization
in the context menu of the subproject can be used to optimise
selected subprojects only.
- The optimisation of personnel resources is done along the
following command structure: employees -> teams -> roles
(explanation: if it includes employees, the optimisation will
ignore teams or roles.)
|