Project controlling
Project controlling consists of the following:
- Entering information regarding the project progress
- Determining effective dates
- Analysing ongoing and yet-to-begin activities
Enter information about the project progress
The updating of information about a selected activity can be
accomplished by entering the activity's percentage of completion at
regular intervals.
In order to enter the activity's percentage of completion, do as
follows:
- Mark the activity you want to enter in the diagram.
- Activate the tab General in the window Activity
properties.
- Enter the percentage into the field Completed.
- Click on the button OK.
Alternative 1: You can enter the percentage of completion
in the context menu of the activity.
Alternative 2: You can enter the percentage of completion
in the table of the bar diagram in the columns Quantity, Effort and
Duration below Completed.
Note: If there is a number of activities linked as
Finish-Start, and if the successor has more
than 0% in the field Completed, its
predecessor is set automatically to the value 100%.
Determine effective date
An effective date is the point in time at which the percentages
were last entered. An effective date is determined by means of a
check mark (a small triangle in the upper part of the
timescale).
Example: Bar diagram with determined effective date and
percentages (black bar in activities).

Analysis of ongoing and yet-to-begin activities
If you have entered the percentage for the selected activity and
determined the check time, you have updated the information about
the progress of the project. You can view the project information
by clicking on the blank space in the window of the main
project.
- Finished - Number of finished
activities.
- Started - Number of already started
activities.
- Yet-to-begin - Number of activities that
have not yet started.
- All - Number of all activities.
- Reserve - Difference in time between the
finish date of the latest activity and the deadline of the
project.
- Completed - Percentage of the project's
progress (is calculated by means of the duration of the activities
only).
- Ongoing and yet-to-begin activities - This
list shows detailed information about activities that have just
started or are ready to be started.
The column Difference shows the variance
between the actual progress of activities and at that time and the
effective date (negative difference: delay / backlog, positive
difference: gain of time).
|