Import text file CSV format
From the text file, you can import the project structure, name
of tasks, and their start dates and finish dates to Rillsoft
Project.
Sample of a text file:
WBS;Name;Start;Finish;Duration, hrs.;Effort, EH;Costs, €
1;Subproject1;25.08.2008 08:00;05.09.2008
17:00;80,00;200,00;10741,20
1.1;Task1;25.08.2008 08:00;29.08.2008 17:00;40,00;40,00;1520,00
1.2;Task2;28.08.2008 08:00;03.09.2008 17:00;40,00;80,00;3040,00
In order to import a text file as CSV file, do as follows:
Step 1:
- Select the menu item File / Import / Text file
in CSV format.
- Activate the check box First row contains only headers, do
not import if the first row should not be imported.
- In the drop down menu Separator for columns, select the
separator you want to use to separate the individual elements from
each other.
- In the drop down menu Date and time format, select the
format you want to use for the display of date and time format in
the text file.
- The table lists information that can be accepted in the
project.
- Click on the button Continue.
Step 2:
-
- In the column Assignation, select a matching name for
the specific property of a product from the drop down menu.
Normally, the names are connected to the values in the column
Columns.
- Click on the button Finish.
See also:
XML,
Export,
Adjusting the XML settings for
the presentation of the project in the internet/intranet.
|