Project management
You can use Rillsoft Project 5.2 for the following tasks, so as
to accomplish the successful completion of your project targets or
even exceed them and prevent the schedule from getting delayed or,
at least, cushion the consequences of possible risks:
- separating completed from yet-to-begin activities.
- shifting delayed activities to the due date (current
date).
- assigning or reassigning employees to and from activities in
the ongoing project.
- assigning personnel to critical activities, so as to speed up
execution.
- optimising resource utilization of not yet completed activities
of the project.
A sample of a project before being updated

Separation of completed from yet-to-begin activities
- Rightclick on the activity and select from the context menu the
command Split / From completed part .
Shift delayed activities to the due date (current date)
- Set the due date.
- Enter the percentages of completion of all activities.
- Select the menu item Project / Shift
activities to due date.
A sample of a project after being updated

Assignation or reassignation of employees to and from
activities in the ongoing project
- Mark the activity.
- Activate the tab Employees in the window
Object properties.
- Remove the employee from the activity.
- Click on the button OK.
Alternatively: You can remove an employee from several
activities at a time. Select the menu item Project
/ Reassign employees from activities.
Assignation of personnel to critical activities, so as to speed
up execution
- Mark the critical activity.
- Activate the tab Employees in the window
Object properties.
- Assign more employees to the activity.
- Click on the button OK.
Optimise resource utilization of not yet completed activities
of the project
- Set the due date.
- Enter the percentages of completion of all activities.
- Select the menu item Project / Optimise
resource utilization.
Note: Delayed activities will be automatically shifted to
the due date during the optimisation of resource utilization.
|