Assign activities to a machine type in Machine type
utilization
Important! A project schedule including activities and
the roles required in the resource pool should already been set up
at this time.
In order to assign activities to a machine type, do the
following:
- Select the view Machine type
utilization.
- Select the menu item Project / Filter.
The dialogue box Filter opens.
- Remove the tick of the check box Offer only
used resources for selection to view all machine types from the
resource pool in the list.
- You can mark the check box Roles and transfer all
machine types to the view Machine type utilization.
Alternatively, you can mark only selected machine
types.
- Click on the button OK.
- Select a machine type which you want to assign activities to in
the table of the view Machine type utilization.
The tab Activities in the window Resource properties lists
activities from the project schedule.
- Mark the check boxes of the activities.
- You can, among others, define the quantity, utilization and
notes of a machine type for an activity.
- Mark the check boxes of the activities.
- Click on the button OK.
Machine type properties during allocation
In this allocation, you can refine role properties by
controlling and defining the following values for each of the
activities:
- Numb er of machine type
- Utilization of machine type
- Notes regarding to a machine type
Selection of activity
During the assignation, you can determine the activity list by
activating /deactivating the following options:
- Assigned activities only, lists only
assigned activities.
Activities at a specific date
You can filter activities that are due at a specific date.
If you leftclick on a cell showing the result from the row Machine
type and column Date, you will only be displayed the activities
that were defined for this particular period of time.
See also:
Assign activities to a
role,
Assign activities to a
team,
Assign activities to an
employee,
Assign activities to a
material,
Assign activities to a
machinery.
|