Assign activities to machines in the view Machine
utilization
Important! A project schedule including activities and
the machines required in the resource pool should already been set
up at this time.
In order to assign activities to a machine, do the following:
- Select the view Machine utilization.
- Select the menu item Project / Filter.
The dialogue box Filter opens.
- Remove the tick of the check box Offer only
used resources for selection to view all machines from the
resource pool in the list.
- You can mark the check box Roles and transfer all
machines to the view Machine utilization.
Alternatively, you can mark only selected machines.
- Click on the button OK.
- Select a machine which you want to assign activities to in the
table of the view Machine utilization.
The tab Activities in the window Resource properties lists
activities from the project schedule.
- Mark the check boxes of the activities.
- You can, among others, define the utilization of a
machine for an activity.
- Mark the check boxes of the activities.
- Click on the button OK.
Machine properties during assignation
In this assignation, you can refine machine properties by
controlling and defining the following values for each of the
activities:
- Availability of a machine
- Utilization of a machine
- Notes regarding to a machine.
Selection of activity
During the assignation, you can determine the activity list by
activating /deactivating the following options:
- Assigned activities only, lists only
assigned activities.
Activities at a specific date
You can filter activities that are due at a specific date.
If you leftclick on a cell showing the result from the row Machine
and column Date, you will only be displayed the activities that
were defined for this particular period of time.
See also:
Assign activities to a
role,
Assign activities to a
team,
Assign activities to an
employee,
Assign activities to a
material,
Assign activities to a machine
type.
|