Assign activities to subprojects
In order to assign activities to subprojects, do as follows:
- Mark the activity bars you want to move into a subproject.
- From the context menu, select Shift to
subproject or click on the icon bar with the same name
Shift to subproject
in the Project bar.
Alternative: You can select the menu item Project /
Shift to subproject.
The dialogue box Select subproject opens.
- In the list, doubleclick on the subproject you want to assign
activities to.
The activities will then be moved to the subproject and the
numbering of activities subordinated to the subprojects if the WBS
code has been set up accordingly.
|