Edit activities
In order to edit any parameter of an existing activity, do as
follows:
- In the diagram, click on the activity whose parameter you want
to edit.
- Activate the required tab in the window Properties and make the
changes.
- Click on the button OK.
Alternative 1: You may make the changes to the most
important activity parameter directly in the table of the bar
diagram.
Alternative 2: You may use the mouse to shift the
activity in the diagram, so as to change its time parameters or
duration.
Alternative 3: You can quickly check the percentage of
completion if you select the menu item Completed in the
context menu.
See also:
Create activities,
Delete activities,
Enter activitiy properties,
Work with activity and subproject
tables.
|