Assign employees
In order to assign employees to the selected activities, do as
follows:
- Activate the tab Employees in the window
Activity properties.
Assigned roles
- Mark the check box of a role in the list Assigned roles in
order to use this role as additional filter for the list of
employees. The list of employees shows you only those employees who
have the appropriate roles and qualifications.
- The column Quantity-utilization-effort contains the required
number of employees whose utilization and effort meet the demands
of the role. This column is deactivated by default. If you want to
unhide it, please refer to Details.
- The field Balance contains the dynamically calculated
difference between the requested effort for a role and the
summarized effort of the already assigned employees with the same
role and qualification. This serves as support during the
controlling of the required assignations of employees. A negative
value, for instance, indicates that more employees with this role
and qualification are required.
Preferred and assigned teams
- Mark the check box Preferred and assigned
teams to use the assigned teams as an additional filter for the
list of employees. The list of employees will show you then only
those employees that belong to assigned teams.
Available employees - The table in the
centre lists you, depending on the filter settings (teams, roles,
and entries in the field filter), all employees defined in the
resource pool and available for being assigned to current
activities.
- Enter a string value into the field Filter
to show only certain employees (search via employee name and code)
or enter two dots ".." in order to view the employees that have
already been used by the project.
- On-call - percentage of the possible
working capacity of an employee within activity duration, adjusted
for the reported non-working days (holidays/sickness).
- Availability - percentage of the possible
working capacity of an employee within activity duration, adjusted
for the participation of the employee in other activities of the
project.
- Mark the check box Check availability in current
portfolio in order to take the employee utilization in other
projects that are part of the last opened portfolio into
account.
You can view the content of the portfolio by leftclicking on the
blank space in the bar diagram and selecting the tab Portfolio
overview.
- Doubleclick on the entry in the central table to assign this
employee to the activity.
Assigned employees
- On-call - percentage of the possible working capacity of
an employee within activity duration, adjusted for the reported
non-working days (holidays/sickness).
- Availability - percentage of the possible working
capacity of an employee within activity duration, adjusted for the
participation of the employee in other activities of the project as
well as the their utilization in this activity.
- Enter a differing value in percent into the field
Productivity if the productivity of the employee in the
activity differs (they are proposed from the resource pool).
- Enter a differing value in percent into the field
Utilization if the utilization of the employee in the
activity differs. If you have reported a role utilization to the
tab Roles, this utilization will be taken over; otherwise, default
utilization is 100%.
- If you click on the icon in the field Absence, the
window Absence with the calendar field opens where you can define
the days the employee will not be participating in the
activity.
- Enter a differing value into the field Effort, for the
effort that an employee has to perform within the activity.
- Enter notes that might be crucial for the employee in
connection with the activity into the the field Notes.
- Mark the check box Utilize resources to the maximum in
order to obtain the shortest possible duration of the activity.
This redistributes the effort of the resources with identical
qualifications in a way to allow for a better utilization of the
resource, which can affect the duration of an activity by, for
instance, a higher percentage of readiness.
- Click on the button OK.
Notes:
- You can adjust the layout of the columns of the three tables at
your convenience by rightclicking on the column names of the table
and selecting the columns you want to adjust.
- In order to have quick access to the used resources, click on
the button Resource pool if you are using the general
resource pool - or on the button Project resources if you
are using a project-specific resource pool.
See also:
Enter activitiy properties,
Define general activity
properties,
Assign roles,
Assign teams,
Allocate material,
Allocate machinery,
Check links,
Define format,
Fill in user-defined
fields,
Enter notes & links.
|