Allocate machinery
In order to allocate machines to the selected activities, do as
follows:
- Activate the tab Machinery in the window
Activity properties.
Allocated machine groups - machine
types
This table lists the allocated machine types in order to support
you in selecting the machinery.
- The marked check box of a machine group / machine type serves
as additional filter for the machinery list. The list Machinery
shows you only those machines that have the corresponding machine
group and machine type.
- The field Quantity-utilization contains the required number of
machines as well as their utilization for the machine type. This
column is deactivated by default. If you want to unhide it, please
refer to Details.
- The field Balance contains the dynamically calculated
difference between the requested number for a machine type and the
total number of the already assigned machines with the same machine
type. Support in the controlling of the required allocations of
machinery. A negative value, for instance, indicates that more
machines of this machine group and machine type are required.
Mark the check box Preferred and assigned
teams to use the assigned teams as an additional filter for the
list Machinery. The list Machinery will show you then only those
machines that belong to the assigned teams.
Available machinery
Depending on the filter settings (teams, machine type and the
entries in the field Filter), the central table shows you the
machinery as defined in the basic resources. Enter a string value
into the field Filter to show only certain
machines (search via the machine group, type and code) or enter two
dots ".." in order to view the machines that have already been used
by the project.
- The field Availability shows the percentage of the possible
working capacity of a machine within activity duration, adjusted
for the participation of the machine in other activities of the
project.
- Mark the check box Check availability in current
portfolio in order to take the employee utilization in other
projects that are part of the last opened portfolio into
account.
You can view the content of the portfolio by leftclicking on the
blank space in the bar diagram and selecting the tab Portfolio
overview.
- Doubleclick on the entry in the central table to allocate this
machine to the activity.
Allocated machines
The right table shows you the machines already selected for the
activity.
- Enter the machine utilization of this activity into the field
Utilization.
- Enter notes that might be crucial for the machine in connection
with the activity into the the field Notes.
- Click on the button OK.
Notes:
- You can adjust the layout of the columns of the three tables at
your convenience by rightclicking on the column names of the table
and selecting the columns you want to adjust.
- In order to have quick access to the used resources, click on
the button Resource pool if you are using the general
resource pool - or on the button Project resources if you
are using a project-specific resource pool.
- The time of use will be calculated automatically.
See also:
Enter activitiy properties,
Define general activity
properties,
Assign roles,
Assign teams,
Assign employees ,
Allocate material,
Check links,
Define format,
Fill in user-defined
fields,
Enter notes & links.
|