Split activities
You can get hold of this function via the context menu of the
activity.
In order to split an existing activity, do as follows:
- Rightclick on the activity in the diagram field.
- Select the command Split from the context
menu and choose one of the following functions:
-
- into several activities
- from the completed part
- at the first shift
- in the event of multiple assignments
Split into several activities

Define the activity parameter according to which you want to split
the activities in the field Split into.
You can choose between the following parameters - Percentage, Working result, Effort, Duration,
Costs.
The values to be entered into the next field need to be separated
by blank spaces.
Mark the check box Create finish-start links
between activities if you want to link the split activities
with each other.
Mark the check box Show in one row if you want
to have the split activities displayed in one row. The list shows
the split activities.
Split from the completed part
This command is activated if a part of an activity has been
completed.
In this event, the split date will be shown in brackets. An
activity is split into two activities, the first is 100% completed,
the second has not yet started.
Split at the first shift
You can choose among the various due dates in the list, which mark
the start of the succeeding shifts.
Split in the event of multiple assignments
This function is activated if two or more activities are executed
at a time and more than one of these activities have been assigned
one and the same resource.
In order to prevent from multiple assigments of aone resource, you
can split one activity before the start of the other activity. You
will find the program offer you automatically the possible dates.
|